Paying a contractor is a balance: they need cash for materials, you need leverage until the work is done. A milestone schedule handles both.
Typical deposits
- Small repairs (under $1,000): often no deposit, pay on completion.
- Mid-size jobs: 10–30% to order materials.
- Custom orders (windows, cabinets): sometimes higher, because products are made to measure. Ask for the supplier order confirmation.
State limits
Some states cap deposits. California limits home improvement down payments to $1,000 or 10% of the contract price, whichever is less. Maryland caps deposits at one-third of the contract price. Check your state's consumer protection office for current rules.
A sample milestone schedule
| Milestone | Payment |
|---|---|
| Contract signed / materials ordered | 10–25% |
| Materials delivered, work started | 25% |
| Substantial completion | 40% |
| Final inspection & punch list done | 10–15% |
Keep a final holdback
Hold the last 10–15% until the punch list is finished, the final inspection passes, and you have lien waivers. It's the most effective way to get the small things done.